Guest jade_yan Posted August 7, 2003 Report Share Posted August 7, 2003 as of 8/1/03, CSC was processing 129's (for fiance) received on 3/31/03. Theferfore, in the last 16 days reported, they processed 11 days of petitions. the backlog grows. Link to comment
robhon Posted August 8, 2003 Report Share Posted August 8, 2003 CSC is pretty volatile. They seem to run anywhere between 3 and 6 months. Almost like they focus on I-129Fs and work them down, but then move on to another visa type. Ye 'ole accordian timeline.Ooooh, being a manufacturing guy, that description runs chills up my spine. I think they could use a good process engineer. Link to comment
owenkrout Posted August 8, 2003 Report Share Posted August 8, 2003 Being a Manufacturing Engineer, I agree with you entirely. However, I actually saw a government web site that stated that this was the process that they followed. No wonder they are so far behind. Link to comment